ITP template for civil works: hold, witness and surveillance points explained
An inspection and test plan (ITP) lists every check on a piece of work: what's inspected or tested, how, against what acceptance criteria, how often, who signs it off, and where the record lives. On civil and roadworks contracts it's usually a contract requirement under the project quality plan. It's also how you prove a lot is conforming before you cover it up.
Templates only, not certified engineering advice. Your contract specification decides the actual hold points, test methods and acceptance criteria.
The columns every ITP needs
| Column | What goes in it |
|---|---|
| # | Step number, in construction order |
| Activity / characteristic | What's being checked, e.g. "trench excavation and bedding" |
| Inspection / test method | Visual, survey, density test, certificate review, CCTV… |
| Acceptance criteria | The requirement, with a reference to the drawing, standard or spec clause |
| Point | H, W or S (see below) |
| Frequency | Per lot, per load, per x m… as the spec requires |
| Record | Where the evidence is filed (test report no., survey file, photo) |
| Checked (sign/date) | Who did the check, and when |
| Released by | For hold points: who released it (usually the client's representative) |
Hold, witness and surveillance points
- H: Hold point. Work must not proceed past this point until the nominated person releases it. Typical examples are bedding before pipes go in, and subgrade before pavement goes down.
- W: Witness point. You give notice so the client's representative can attend. If they don't come within the notice period, work can usually continue. Check your contract for the notice period.
- S: Surveillance / record. It's checked and recorded by the contractor, and available for audit.
The contract specification sets which points are holds. Where a contract adopts Queensland Department of Transport and Main Roads specifications, the hold and witness points are set out in the relevant MRTS document, e.g. MRTS03 Drainage Structures, Retaining Structures and Slope Protections (TMR technical standards). Insert the clause and table numbers from the version named in your contract.
Worked example: stormwater pipe laying
This is the structure of our ITP-03. H/W/S defaults are suggestions only; set them to match your contract.
| # | Activity | Method | Acceptance criteria | Point |
|---|---|---|---|---|
| 1 | Materials receipt (pipes) | Visual; certificates | AS/NZS 4058 (concrete pipes) or per spec | W |
| 2 | Trench excavation & bedding | Measure; visual | Bedding type/thickness per drawings | H |
| 3 | Pipe laying: line & grade | Survey | Per drawings & tolerance | W |
| 4 | Joints | Visual | Sealed per manufacturer | W |
| 5 | Haunch & backfill compaction | Density test | Per spec | S |
| 6 | Post-install inspection | CCTV / visual | No defects beyond limits | H |
Keep a hold point register
A one-page hold point register across all your ITPs stops the usual argument about whether a hold was released. Each row records the ITP and lot, the point type, the description, when notice was given, who released it and when, and any NCR reference. Keep it live and attach it to each lot's conformance package.
Common ITP mistakes
- Copying acceptance criteria as "per spec". Name the clause or table, so the person checking knows exactly what to check against.
- Hold points the contract doesn't require, or missing ones it does. Map every hold point in the spec to an ITP line.
- No frequency. "Density test" with no frequency invites a dispute about whether you tested enough.
- Records that don't link. The record column should point to a test report or survey file someone can find a year later.
- Signing before the check. The sign/date column is evidence; sign it only after the test result is in.
Ready-made civil ITPs
The QLD Civil SWMS + ITP Pack (A$149) includes 7 editable Word ITPs plus the hold point register: earthworks, subgrade and unbound granular pavement, stormwater pipe laying, kerb and channel, concrete footpaths, asphalt surfacing and line marking. It also has 8 SWMS for high risk civil work.
Only need one? Each document is also sold on its own (Word, editable):
| ITP | Price |
|---|---|
| Earthworks (MRTS04) | A$19 |
| Subgrade and unbound granular pavement (MRTS05) | A$19 |
| Stormwater pipe laying | A$19 |
| Kerb and channel | A$19 |
| Concrete footpaths | A$19 |
| Asphalt surfacing (MRTS30) | A$19 |
| Line marking (MRTS45) | A$19 |
Each single ITP includes the hold point register.
Templates only, not certified engineering advice. Not affiliated with or endorsed by the Department of Transport and Main Roads. Built from public information only.
Free download
Grab AU Civil Quick Calcs free (A$0+) on our store. It's the quickest way to try our templates.
Get the free calculatorsSources
- Queensland Department of Transport and Main Roads, technical standards and publications: https://www.tmr.qld.gov.au/business-industry/technical-standards-publications
- TMR, MRTS03 Drainage Structures, Retaining Structures and Slope Protections: https://www.tmr.qld.gov.au/-/media/busind/techstdpubs/Specifications-and-drawings/Specifications/3-Roadworks-Drainage-Culverts-and-Geotechnical/MRTS03.pdf